Aurora, Illinois

File #: 24-0238    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/28/2024 In control: City Council
On agenda: 4/23/2024 Final action: 4/23/2024
Title: A Resolution to award the Hoyles Avenue and Jackson Street Sewer Separation and Water Main Replacement project located in Ward 3 to Fox Excavating Inc. of Batavia, IL in the bid amount of $939,285.00.
Attachments: 1. Exhibit A - Location Map, 2. Exhibit B - Ad for Bid, 3. Exhibit C - Bid Tab, 4. Exhibit D - Advertised Bid Documents, 5. Exhibit E - Contractor Submittal
cover
TO: Mayor Richard C. Irvin


FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: April 8, 2024

SUBJECT:
A Resolution to award the Hoyles Avenue and Jackson Street Sewer Separation and Water Main Replacement project located in Ward 3 to Fox Excavating Inc. of Batavia, IL in the bid amount of $939,285.00.

PURPOSE:
To install a new storm sewer removing stormwater from the combined sewer system at several locations on Hoyles Avenue and a portion of Jackson Street. Water main replacement has been deemed necessary on Hoyles Avenue between 5th Street and Jackson Street to improve water quality and system capacity. The existing 4" water main will be replaced with an 8" ductile iron water main and confirmed lead water services will be replaced.

BACKGROUND:
A new storm sewer will be installed to remove surface drainage flows from the combined sewer system. A location map is attached as Exhibit A to show the limits of the project. This project will help satisfy the requirements associated with the City's Long Term Control Plan and the City's Illinois Environmental Protection Agency Combined Sewer System Overflow. Lead water services within the project corridor will be replaced with the approval of each homeowner.

DISCUSSION:
The proposed improvements have been publicly advertised and bid in conformance with City procedures. The advertisement for bid is attached as Exhibit B. Seven conforming bids were received, publicly opened and read aloud on March 27, 2024. The bid tabulation, the advertised bid documents and Fox Excavating, Inc.'s bid are attached as Exhibits C, D and E, respectively.

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

Portions of the project are accounted for within three 2024 budgets. $381,300.00 within account 510-4058-511-73-02 (IC076, $5,000,000.00 Water Main Replacement), $165,520.00 within account 510-4058-511-73-02 (IC080, $3,000,000.00 Lead Water Service Line Replacement), and...

Click here for full text