Title: A Resolution To approve the payment for landscape design, construction administration, and bidding/negotiation services from Dewberry Architects Inc. of Elgin, IL for the replacement fire station #7 project in the amount of $102,280.00.
Attachments: 1. 15-35 Fire Station Final .pdf, 2. 16_0408 Aurora FS#7 design presentation - low res.pdf, 3. COA legal approval for Dewberry.pdf, 4. Dewberry for fire station 7.pdf
cover
TO: Mayor Robert J. O'Connor

FROM: Don Davids, Assistant Fire Chief

DATE: December 5, 2016

SUBJECT:
Finance Committee approval of the payment to Dewberry Architects Inc. of Elgin, IL. for the landscape design, construction administration and bidding/negotiation phase of replacement Station #7 in the amount of $102,280.00.

PURPOSE:
To have the replacement fire station #7 landscape design, bidding/ negotiation, construction administration approved and completed.

BACKGROUND:
A Capital Improvement Plan for the replacement of Station #7, built in 1957, was originally submitted in 2007. The plan proposed that the design and engineering phase of the project take place in one year followed by building construction during the next year. Funds were approved in the 2016 budget to move forward with the design and engineering phase of the project which has been completed. The next step includes the landscape design, construction administration and bidding/negotiation for the station construction.

DISCUSSION:
The completion of the design and engineering phase of the Fire Station #7 project will allow for construction to begin in 2017. Construction of a new station will address the various issues of the 57 year old building such as limited space for parking modern fire apparatus, building mortar deterioration, as well as aging plumbing and electrical fixtures and infrastructure. In addition, a new facility will allow for the addition of a 7th ambulance to serve the City.

The contract that included the landscape design, construction administration and bidding/negotiation that was presented by Dewberry Inc. has been reviewed and approved by our legal department and is attached. Funds for the landscape design and construction administration phase are available in the 2017 budget in account #340-3033-422.72-35 of the Capital Improvement Fund A.

IMPACT STATEMENT:
During the landscape design and construction administration phase other divisions in the City may need ...