TO: Mayor Thomas J. Weisner

FROM: Eric J. Gallt, City Traffic Engineer

DATE: June 7, 2016

SUBJECT:
A resolution awarding Roundabout Intersection Improvements for Highland Avenue and Sullivan Road construction to the low bidder, Geneva Construction Co.

PURPOSE:
To award the Roundabout Intersection Improvements for Highland Avenue and Sullivan Road construction to the low bidder, Geneva Construction Co.

BACKGROUND:
Highland Avenue and Sullivan Road has had safety concerns with regards to the crash history hence an all way stop sign was installed to address the issue. Since its installation, the intersection has experienced significant peak hour delays. The traffic has been observed to back all the way up to Lake Street to its east and significant backing up on the west as well. The City has been wanting to bring improvements to the intersection and after evaluating various intersection alternatives for overall delay, safety and cost effectiveness, it was proposed to have a modern roundabout installed at Highland Avenue and Sullivan Road.

DISCUSSION:
A proposed roundabout will replace the current all way stop controlled intersection. The project limits are approximately 250 feet east, 330 feet west and 400 feet south of the intersection of Highland Avenue and Sullivan Road. The work involves pavement removal, earth excavation, PCC pavement, combination concrete curb and gutter, pavement marking, landscaping, erosion and sediment control and collateral work necessary to complete the project.

Three bids were received and the bid tabs are provided for your use. The low bidder was Geneva Construction Co. at $ 526,348.68

The following funds will be utilized:

GB120 Highland & Sullivan Intersection Improvements 340 4460 431 73 23 $404,700
A budget transfer is anticipated that covers the difference amount of $122,341.20.


IMPACT STATEMENT:
The intersection will be closed during the construction of the roundabout and t...