TO: Mayor Richard C. Irvin
FROM: Kurt Muth, PE, Engineering Coordinator
DATE: February 10, 2024
SUBJECT:
A Resolution to award the Middlebury Dr to LaJolla Ct Water Main project located in Ward 9 to H. Linden & Sons Sewer and Water, Inc. in the bid amount of $438,280.
PURPOSE:
Water main installation has been deemed necessary between Middlebury Drive to LaJolla Ct to increase system capacity. The City's engineering consultant modeled the water distribution system in anticipation of the Lincoln Prairie development in the southeast area end of the system and identified two necessary water main extensions to serve potential commercial development at that location. This is the last of those two locations. As part of the development agreement, the Pulte Group will be reimbursing the city for the cost of this project including all City of Aurora engineering division efforts to design, permit and manage the construction of this project. A 12" HDPE water main are being installed via directional drilling.
BACKGROUND:
A location map is attached as Exhibit A to show the limits of the project. Portions of the proposed water main are crossing ComEd and Fox Valley Park District (FVPD) property, a water main easement with ComEd is currently in progress and the water main easement for FVPD has been obtained. There are no services located within the project limits.
DISCUSSION:
The proposed improvements have been publicly advertised and bid in conformance with City procedures. The advertisement for bid is attached as Exhibit B. Five conforming bids were received, publicly opened and read aloud on July 24, 2024. The bid tabulation and H. Linden & Sons Sewer and Water, Inc.'s bid are attached as Exhibits C and E.
At the time of the bidding, construction was proposed to be in 2024, but due to the length of time it has taken to acquire a water main easement with ComEd, construction will happen in 2025. Due to inflation of material, H. Linden & Sons has requested a...
Click here for full text