TO: Mayor Thomas J. Weisner
FROM: Eric J. Gallt, City Traffic Engineer
DATE: July 7, 2016
SUBJECT:
A Resolution Approving a Phase 3 Engineering Contract with Thomas Engineering Group for the Highland and Sullivan Intersection Improvements
PURPOSE:
To Obtain Approval for a Resolution for a Phase 3 Engineering Contract with Thomas Engineering Group for the Highland and Sullivan Intersection Improvements.
BACKGROUND:
A Phase III or construction oversight consultant is required for the intersection improvements. The work on this intersection is scheduled to begin by the end of July.
DISCUSSION:
Thomas Engineering Group was selected to oversee the Phase III construction of the Highland and Sullivan Intersection Improvements. Funding is made available through the following account:
Capital Improvements Other 340 4460 431 73 99 $70,000
IMPACT STATEMENT:
No Impact
RECOMMENDATIONS:
Staff recommends approval of the Phase 3 Engineering Contract with Thomas Engineering Group for the Highland and Sullivan Intersection Improvements.
cc: Alderman O'Connor, Chairman
Alderman Mervine
Alderman Bohman
Alderman Mesiacos, Alternate
CITY OF AURORA, ILLINOIS
RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution Approving the Phase 3 Engineering Contract with Thomas Engineering Group for the Highland and Sullivan Intersection Improvements for $70,000.
body
WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and
WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and
WHEREAS, the City desires to have construction oversight for the Highland and Sullivan Intersection Improveme...