Title: A Resolution accepting the improvements and maintenance security for Aurora University - New Dormitory, 398 S Evanslawns Av.
Attachments: 1. 2023-09-05 Cover Letter, 2. Location Map
cover
TO: Mayor Richard C. Irvin

FROM: Jason Bauer, P.E. - Assist. Dir. Of Public Works - Assist. City Engineer

DATE: September 12, 2023

SUBJECT:
A Resolution to accept the public improvements and maintenance security for the completed Aurora University - New Dormitory, 2021.161, 398 S Evanslawn Av., in Aurora, Illinois Ward 4

PURPOSE:
To accept the public improvements installed by the Developer of this project and to approve the establishment of the required, one year, 20% maintenance security for these improvements.

BACKGROUND:
This is a commercial development that constructed a new dormitory in Aurora which included public improvements. In accordance with Section 43-55(a)(3) of Aurora's Municipal Code, the Developer of the Project posted a security to ensure completion of these proposed public improvements including, a water main system and a driveway approach for the site.

DISCUSSION:
This development has now completed all installations, inspections and submissions that make it eligible to be recommended by the Engineering Division for final acceptance of these improvements and for the Developer to establish the required one year maintenance security. As required by Section 43-103(c) of the Municipal Code, the Engineering Division has reviewed, approved and filed as-constructed record plans of the development which depict these public improvements and has completed and approved a final site inspection of said improvements via our onsite consultant. Based on our review and approved site inspection, it is recommended by the Engineering Division, that City Council accept the public improvements, and as a condition of this acceptance require that the developer submit the required one year maintenance security at a value of 20% of the original developments security.

IMPACT STATEMENT:
This action adds or replaces public infrastructure - utilities to various divisions for maintenance, including the Division of Water and Sewer Maintenance; the Water Productio...

Click here for full text