cover
TO: Mayor Richard C. Irvin
FROM: Kurt Muth, P.E., Engineering Coordinator
DATE: February 13, 2023
SUBJECT:
A resolution to award the 2023 Citywide Pavement Patching for Water and Sewer Maintenance to Schroeder Asphalt Services, Inc., P.O. Box 831, Huntley, IL 60142
PURPOSE:
This is an annual project that is required to patch pavement in the public right of way that was damaged in relation to utility repairs such as water main breaks and sanitary sewer repairs. Schroeder Asphalt Services, Inc. has completed similar projects in the past and has performed satisfactory work
BACKGROUND:
This project was bid publicly, with an advertisement in the Aurora Beacon News on January 15th, 2023. The proof of the advertisement is attached as Exhibit A. Bids were received, opened and read aloud publicly on February 1st, 2023. Three bids were received with the tabulation of those bids attached hereto and incorporated as Exhibit B. The lowest responsible bid was from Schroeder Asphalt Services, Inc. of Huntley, IL in the amount of $738,400.00. A copy of the submitted bid is attached as Exhibit C. The lowest bid came in approximately 2.4% below the engineer's estimate. It is anticipated that a small portion of this contract will be used to address individual utility repairs performed by contractors to take advantage of better restoration prices.
This bid is required to follow the City's Local Preference Ordinance, however, there was only one bid received from a certified local vender, Geneva Construction, Co. of Aurora, IL, in the amount of $856,850.00, 16% higher than the lowest bid which is outside the percentage which would allow them to match the lowest bid.
DISCUSSION:
This Citywide project will benefit the entire community, as it is the only contract that will be in place to repair the roadways that are damaged throughout the year due to utility repairs. This work is budgeted on an annual basis. This contract shall have a maximum value of $738,400.00 budge...