TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: November 12, 2020

SUBJECT:
A Resolution allowing the Director of Purchasing to approve Change Order 1 for $100,000 to the Contract of $802,630.00 with Geneva Construction Co., P.O. Box 998, Aurora, IL 60507-0998 for the 2020 Citywide Pavement Patching for Water and Sewer Maintenance Project.

PURPOSE:
In order to make modifications to an existing contract, City Council approval is required. Approval of Change Order 1 (attached as Exhibit A) will modify the existing Contract with Geneva Construction Co., to account for additional hardscape surface restoration resulting from dig repairs to underground infrastructure.

BACKGROUND:
This project was bid publicly, with an advertisement in the Aurora Beacon News on February 16, 2020. The lowest responsible bid was from Geneva Construction Co. of Aurora, IL in the amount of $802,630.00. A copy of the original bid is attached as Exhibit B. The lowest bid came in approximately 5% below the engineer's estimate. The quantities of required hardscape restoration are estimated at the beginning of each year based on historical quantities. The changed order requested is $100,000.00 which is approximately 13% more than the original contract amount.

DISCUSSION:
This Citywide project will benefit the entire community, as it is the only contract that will be in place to repair the roadways that are damaged throughout the year due to utility repairs. This work is budgeted for on an annual basis. The original contract had a maximum value of $802,630.00 and had funds budgeted in 2020 within Account Number 510-4063-511-38-38 ($664,750.00) and $68,940 each from Account Number 510-4063-511-73-14 (Sanitary Sewer Evaluation and Repair, IB018, 2020 Budget amount of $4,750,000) and Account Number 510-4058-511-73-02 (Water Main Evaluation, Repair and Replacement, IC076, 2020 Budget amount of $5,700,000). The change order requested would be split ev...

Click here for full text