TO: Mayor John Laesch
FROM: Steve Andras, P.E., Airport Manager
DATE: November 25, 2025
SUBJECT:
A resolution authorizing the Mayor and City Clerk to amend a Design Phase Engineering Agreement in the not-to-exceed amount of $6,000 and to amend a Construction Phase Engineering Agreement in the not-to-exceed amount of $10,100 for the Rehabilitate Airfield Lighting Vault (ARR-4915) and Replace Vault Generator (ARR-5117) projects located at the Aurora Municipal Airport.
PURPOSE:
This resolution will approve a $6,000 second amendment to a design phase engineering agreement with the City's aviation consultant Crawford, Murphy and Tilly, Inc. approved under resolutions R24-053 and R25-052. The proposed resolution will also approve an amendment to a construction phase engineering agreement in the amount of $10,100 with Crawford, Murphy and Tilly, Inc.
BACKGROUND:
The reason for these amendments arises from a rebidding of these projects by the State Division of Aeronautics. The original bid date was November 8, 2024 and the low bidder was Hecker and Company. Since the State was unable to provide a contract to Hecker within the prescribed 90 day period, the project was rebid on September 19 of this year. Again, Hecker prevailed as the low bidder.
The amendments and their associated dollar amounts have been approved by the Illinois Department of Transportation, Division of Aeronautics and are based on the increase in hourly rates over this period.
As stated in prior documents for these projects. The total estimated cost for both projects is estimated to be $1.3M. Once State and Federal grants have been applied, the City's share for both projects is $65,000. Any payments made by the City over this amount will be reimbursed back to the City after completion of these projects.
DISCUSSION:
The total project costs have been set aside under CIPs D052 and D057 in accounts 504-4454-433.73-99 and 504-4454-433.63-34 respectively.
IMPACT STATEMENT:
These two proj...