Legislation Details

File #: 26-0726    Version: 1
Type: Resolution Status: Forwarded to Committee of the Whole
File created: 11/3/2026 In control: Building, Zoning, and Economic Development Committee
On agenda: 11/12/2026 Final action:
Title: A Resolution authorizing the Mayor and City Clerk to Amend a Design Phase Engineering Agreement in the not-to-exceed amount of $19,600 between Crawford, Murphy and Tilly, Inc. and the City of Aurora for the Rehabilitate Auto Parking Lots and Entrance Road Project (ARR-4544) located at the Aurora Municipal Airport.
Attachments: 1. Amendment ARR-4544 Rehab. Auto Parking Lot and Entr. Rds_Design Phase 8.25.26, 2. ARR-4544 Design Amendment Fee approval, 3. ARR-4544 Cover Letter Rehab Auto Parking Lots Entr Rd DPS Amendment 8.27.26
cover
TO: Mayor John Laesch

FROM: Steve Andras, P.E., Airport Manager

DATE: November 3, 2026

SUBJECT:
A resolution authorizing the Mayor and City Clerk to Amend a Design Phase Engineering Agreement in the not-to-exceed amount of $19,600 between Crawford, Murphy and Tilly, Inc. and the City of Aurora for the Rehabilitate Auto Parking Lots and Entrance Road Project (ARR-4544) located at the Aurora Municipal Airport.

PURPOSE:
To obtain City Council approval to amend a design phase engineering agreement with Crawford, Murphy and Tilly, Inc. for project ARR-4544.

BACKGROUND:
This project and original design phase engineering agreement was approved by City Council under resolution R23-034 in February of 2023.
The project was designed and let out for bid through the State of Illinois Division of Aeronautics over two years ago. Due to legal matters between the State and the contractor a contract was never awarded. Nearly three years later the dispute was resolved, and the contractor was authorized to construct the project using their original bid prices. The contractor declined and the project will be rebid this month.

Consequently, a significant amount of design work was required to modify the plans, cost estimate and scope of the project to reduce project costs, offsetting construction price increases. The value of this design work is $19,600 and has been reviewed and approved by the State Division of Aeronautics and will require an amendment to the original design phase engineering agreement with the City's aviation consultant, Crawford, Murphy and Tilly.

DISCUSSION:
The total cost for this project was estimated to be $1,611,093. The City's Local Share was approved under resolution R24-168 in the amount of $306,093, approximately 19%. The total project cost will be known once the bid results are available later this month. Funds for this project have been set aside in the airport's budget under CIP D055 in account number 504-4454-433.73-99.

IMPACT STATEME...