Title: A Resolution to award the Fox Valley Center Drive Water Main Replacement project, located in Ward 10 to Fox Excavating, Inc., in the bid amount of $209,835.00.
Attachments: 1. Exhibit A - 25-154 Location Map - Fox Valley Center Drive Water Main Replacement, 2. Exhibit B - 25-154 Posted Bid Document - Fox Valley Center Drive Water Main Replacement, 3. Exhibit C - 25-154 Evaluation Tabulation - Fox Valley Center Drive Water Main Replacement, 4. Exhibit D - 25-154 Submitted Bid - Fox Valley Center Drive Water Main Replacement
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: May 12, 2025

SUBJECT:
A resolution to award the Fox Valley Center Drive Water Main Replacement project, located in Ward 10, to Fox Excavating, Inc., in the bid amount of $209,835.00.

PURPOSE:
To replace the existing water main in the area which has a history of frequent breaks.

BACKGROUND:
The location of the water main to be replaced can be seen in the attachment, Exhibit A - Location Map. There are a total of 2 water services off the existing water main that will be partially replaced and switched over to the new main. Both water services are copper and will only require a partial replacement to the new Bbox location.

DISCUSSION:
A total of seven bids were received, opened, and reviewed on April 30, 2025. Attached are Exhibits B & C, the posted bid document and the Evaluation Tabulation. Fox Excavating, Inc.'s Submitted Bid can be seen in the attached Exhibit D. The lowest responsible bid received was in the amount of $209,835.00 by Fox Excavating, Inc. This was 13.4% below the Engineer's Estimate of $242,710. The water main improvements will be funded with account 510-4058-511-73-02 (IC076) which has a 2025 total budgeted amount of $4,150,000.00.

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

IMPACT STATEMENT:
This project will be within a commercial area. The surrounding businesses will experience minimal disturbances to their day-to-day operations and have been informed of the upcoming project. General impacts to traffic will be kept to a minimum. Water shutdowns during the project will be planned and coordinated with the businesses affected.

RECOMMENDATIONS:
I request the proposed resolution awarding the contract to Fox Excavating, Inc. in the bid amount of $209,835.00 be adopted.