Title: A Resolution Approving a Final Plan for Lots 1-6 of Butterfield Phase II Unit 5A Subdivision, located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road, for a Warehouse, Distribution and Storage Services (3300) Use in the form of a data center complex
Attachments: 1. Exhibit "A-1" Final Plan - 2023-02-16 - 2023.067, 2. Exhibit "A-2" Landscape Plans - 2023-02-16 - 2023.067, 3. Exhibit "A-3" Building and Signage Elevations - 2023-02-06 - 2023.067, 4. Land Use Petition and Supporting Documents - 2023-02-06 - 2023.067, 5. Plat of Survey - 2023-02-06 - 2023.067, 6. Fire Access Plans - 2023-02-16 - 2023.067, 7. Location Map - 2023-02-16 - 2023.067, 8. Presentation - 2023-01-18 - 2022.368, 9. Appealable Sheet - Final Plan - 2023-02-23 - 2023.067
cover
TO: Mayor Richard C. Irvin

FROM: Planning and Zoning Commission

DATE: February 23, 2023

SUBJECT:
A Resolution Approving a Final Plan for Lots 1-6 of Butterfield Phase II Unit 5A Subdivision, located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road, for a Warehouse, Distribution and Storage Services (3300) Use in the form of a data center complex (Seefried Properties - 23-0146 / NA05/1-23.067 - FSD/FPN - JM - Ward 10)

PURPOSE:
The Petitioner Seefried Properties is requesting approval of a Final Plan for Lots 1-6 of Butterfield Phase II Unit 5A Subdivision located at 2815 Bilter Road, being south of Bilter Road and west of N. Eola Road, for a Warehouse, Distribution and Storage Services (3300) Use, limited to a data center complex which includes the development of a three-building data center complex.

BACKGROUND:
The Subject Property is currently vacant with PDD Planned Development District zoning, which is part of the Butterfield Planned Development.

The Petitioner is requesting approval of a Final Plan for Lots 1-6 of Butterfield Phase II Unit 5A Subdivision for a Warehouse, Distribution and Storage Services (3300) Use, limited to a data center complex. The details of the request include a phased development of three electronic data center buildings consisting of two 209,967 square foot buildings and one 415,934 square foot building. An electrical substation will be constructed to support the electrical requirements of the data centers, which substation will also provide stability to the area electrical grid. In addition, a passenger vehicle electric charging area will be made available and will be located abutting Bilter Road. The lot will begin with a minimum of five spaces with plenty of spaces to grow as the need requires. An area beside the electric charging station will be available for future retail use.

The data center will be accessed from a full entrance on Bilter Road across from the main entrance of the c...