Title: A Resolution to Award the contract for the N. Elmwood Drive & Pleasure Court Water Main Replacement & Storm Sewer Extension project to Patnick Construction, Inc., 9760 Franklin Park Avenue, #504, Franklin Park, Illinois 60131 in the amount of one million, eight hundred seventy-one thousand, seven hundred eighty-nine dollars and zero cents ($1,871,789.00).
Attachments: 1. Exhibit A - Location Map.pdf, 2. Exhibit B - Ad for Bid.pdf, 3. Exhibit C - Elmwood Dr. & Pleasure Ct. Water Main Replacement Bid Tab.pdf, 4. Exhibit D - Patnick Submitted Bid.pdf
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: February 10, 2020

SUBJECT:
A resolution to award the N. Elmwood Drive & Pleasure Court Water Main Replacement & Storm Sewer Extension project located in Wards 4 & 6 to Patnick Construction, Inc., 9760 Franklin Park Avenue, #504, Franklin Park, Illinois 60131 in the bid amount of one million, eight hundred seventy-one thousand, seven hundred eighty-nine dollars and zero cents ($1,871,789.00).

PURPOSE:
To replace the 6" and 8" water main along the Pleasure Court loop and on N. Elmwood Drive from Pleasure Court north to Colorado Avenue. The Elmwood Drive water main has broken several times very recently and the Pleasure Court has a longer history of breaks.

BACKGROUND:
The location of this water main to be replaced can be seen in the attached Exhibit A - Location Map. These two sections of 6" and 8" water main were planned to be replaced in 2020 but due to several breaks on the Elmwood water main, the project time was accelerated with a start date now in February 2020. Closures of entrances to the businesses and residences will be kept to a minimum during construction.

There is currently very limited drainage infrastructure on the entire Pleasure Court loop. This project will add 16 drainage structures and 1,110 feet of storm sewer to improve the drainage conditions.

DISCUSSION:
Nine bids were received, opened, and read aloud on February 2, 2020. The bid tabulation can be seen in the attached Exhibit C. The lowest responsible bid in the amount of $1,871,789.00 was submitted by Patnick Construction, Inc. The water main improvements ($1,596,789.00) will be funded with account 510-4058-511-73-02 (IC076) which has a 2020 budget amount of $5,700,000.00. The storm sewer improvements ($275,000.00) will be funded with account 280-1852-512-81-23 (B037) which has a 2020 budget amount of $593,000.00. Also included as Exhibits B & D are the advertisement for bid and Patnick Con...