Legislation Details

File #: 26-0381    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/15/2026 In control: City Council
On agenda: 6/23/2026 Final action:
Title: A Resolution accepting the improvements and maintenance security for PAS Plaza, 1895 Butterfield Rd.
Attachments: 1. Location Map, 2. 2026-06-16 Cover Letter
Date Ver.Action ByActionResultAction DetailsAgenda DetailsAudio
No records to display.
cover
TO: Mayor John Laesch

FROM: Jason Bauer, Director of Public Works

DATE: June 23, 2026

SUBJECT:
A Resolution to accept the public improvements and maintenance security for the completed PAS Plaza, 2022.251, 1395 Butterfield Rd in Aurora, Illinois Ward 1

PURPOSE:
To accept the public improvements installed by the Developer of this project and to approve the establishment of the required, one year, 20% maintenance security for these improvements.

BACKGROUND:
This is an existing commercial development that constructed an addition in Aurora which included public improvements. In accordance with Section 43-55(a)(3) of Aurora's Municipal Code, the Developer of the Project posted a security to ensure completion of these proposed public improvements including, sanitary sewer system, driveway approach, water main system and storm water management facilities for the site.

DISCUSSION:
This development has now completed all installations, inspections and submissions that make it eligible to be recommended by the Engineering Division for final acceptance of these improvements and for the Developer to establish the required one year maintenance security. As required by Section 43-103(c) of the Municipal Code, the Engineering Division has reviewed, approved and filed as-constructed record plans of the development which depict these public improvements and has completed and approved a final site inspection of said improvements via our onsite consultant. Based on our review and approved site inspection, it is recommended by the Engineering Division, that City Council accept the public improvements, as well as; require as a condition of this acceptance that the developer submit the required one year maintenance security at a value of 20% of the original developments security.

IMPACT STATEMENT:
This action adds or replaces public infrastructure - utilities to various divisions for maintenance, including the Division of Water and Sewer Maintenance; the Water Production ...