cover
TO: Mayor Thomas J. Weisner
FROM: Stephen K. Andras, P.E.
DATE: March 17, 2014
SUBJECT:
A resolution authorizing the Mayor and City Clerk to execute a not to exceed agreement in the amount of $55,500 between Crawford, Murphy & Tilly, Inc. and the City of Aurora for Construction Phase Engineering and Special Services for the Clean and Seal Joints on Runway 15/33 Project at the Aurora Municipal Airport.
PURPOSE:
To obtain City Council approval to enter into an agreement with Crawford, Murphy and Tilly, Inc.to provide Construction Engineering and Special Services for the Clean and Seal Joints on Runway 15/33 Project.
BACKGROUND:
This project is needed to repair and reseal construction joints and replace concrete panels on runway 15/33 and its taxiway.
DISCUSSION:
This project will be constructed under the Airport Improvement Program and will be funded 91% Federal Government / 9% Local share (see attachment Project Status Report).
IMPACT STATEMENT:
This project should have no adverse impact to the City of Aurora and is anticipated to reduce the ongoing cost of maintaining the airport infrastructure.
RECOMMENDATIONS:
We respectfully request that you forward this agreement to the Finance Committee for their review and favorable recommendation.
cc: Alderman O'Connor, Chairman
Alderman Mervine
Alderman Bohman
Alderman Peters, Alternate
CITY OF AURORA, ILLINOIS
RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution Authorizing the Mayor and City Clerk to execute a not to exceed agreement in the amount of $55,500 between Crawford, Murphy & Tilly, Inc. and the City of Aurora for Construction Phase Engineering and Special Services for the Clean and Seal Joints on Runway 15/33 Project at the Aurora Municipal Airport.
body
WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of th...
Click here for full text