Legislation Details

File #: 26-0584    Version: 1
Type: Resolution Status: Forwarded to Committee of the Whole
File created: 9/14/2026 In control: Infrastructure and Technology Committee
On agenda: 9/21/2026 Final action:
Title: A Resolution authorizing the award of a contract to Lorig Construction Company in the amount of $328,620.00 for the 2026 Bridge Rehabilitation Program.
Attachments: 1. Exhibit A - Posted Bid Documents, 2. Exhibit B - Bid Tab, 3. Exhibit C - Lorig Construction Company Submitted Bid, 4. Exhibit D - Lorig Construction Letter of Good Standing
cover
TO: Mayor John Laesch and City Council

FROM: Tim Weidner, P.E., Engineering Coordinator

DATE: September 21, 2026

SUBJECT:
A Resolution authorizing the award of a contract to Lorig Construction Company in the amount of $328,620.00 for the 2026 Bridge Rehabilitation Program.

PURPOSE:
To award a Construction Contract for various bridge maintenance and repair items on 2 bridges within the City.

BACKGROUND:
The City inspects and maintains 36 bridges on the local street network. To ensure public safety, the City of Aurora's bridges are inspected according to the Federal Highway Administration (FHWA) National Bridge Inspection Standards (NBIS). The inspection data is used by the Illinois Department of Transportation (IDOT) to allocate funding for bridge projects. The Engineering Division also reviews the reports to monitor bridge conditions, and plan for repairs and maintenance activities.

Based on the inspection reports and recommended work, the Engineering Division went out to bid for a project that included the scope of work on the following bridges.

Structure




Number
Location
Crossing
Scope of Work

045-6052
Farnsworth Ave
BNSF RR
Expansion Joint Replacement

045-9942
Ohio Street
BNSF RR
Minor Expansion Joint and MSE Wall Repairs

.

DISCUSSION:
This project was advertised on September 2, 2026 on the City's Procurement website. Bids were opened and publicly read through the Procurement website on September 16, 2026. The posted bid documents (without the For Information Only components) are attached as Exhibit 'A'. The bid tabulation and evaluation for the two bids received is attached as Exhibit 'B'. The lowest responsible bid was submitted by Lorig Construction Company of Des Plaines, IL in the amount of $328,620.00 which is 18.1% less than the Engineer's Cost Estimate of $401,150.00.

The local preference ordinance applies to this project, however, no local Aurora contractors bid.

Lorig Construction Company is an IDOT prequ...

Click here for full text