File #: 25-0900    Version: Name: Loaves & Fishes Community Services / 560 Exchange Court & 580 Exchange Court / Moratorium Hardship Appeal
Type: Resolution Status: Passed
File created: 10/30/2025 In control: City Council
On agenda: 11/25/2025 Final action: 11/25/2025
Title: A Resolution Approving a of a Moratorium Hardship Appeal for a warehouse on property located at 560 Exchange Court and 580 Exchange Court.
Attachments: 1. Exhibit "A" Legal Description - 2025-11-20 - 2025.357, 2. Moratorium Hardship Appeal Application - 2025-10-27 - 2025.357, 3. Hardship Letter - 2025-10-27 - 2025.357, 4. PowerPoint Presentation - 2025-11-24 - 2025.357, 5. O25-064, 6. Maps, 7. Legistar History Report - 2025-11-21 - 2025.357
cover
TO: Mayor John Laesch

FROM: Planning and Zoning Commission

DATE: November 20, 2025

SUBJECT:
A Resolution Approving a Moratorium Hardship Appeal for a warehouse on property located at 560 Exchange Court and 580 Exchange Court (Loaves & Fishes Community Services - 25-0900 / NA21/1-25.357 - MHA - TV - Ward 10)

PURPOSE:
The Petitioner, Loaves & Fishes Community Services, is requesting approval of a Moratorium Hardship Appeal to allow construction of a proposed addition to the existing warehouse prior to the expiration of the moratorium, for the property located at 560 Exchange Court and 580 Exchange Court

BACKGROUND:
On September 25, 2025, the City Council approved an 180-day moratorium on data center facilities and warehouses in all zoning districts to allow Staff time to establish zoning regulations for these uses.

As part of the approved ordinance, an applicant may seek an exception from the moratorium pursuant to Section 8 Hardship Appeals Process (see attached ordinance).

To obtain this exception, the applicant must demonstrate by clear evidence that:

i. The effect of the Temporary Moratorium has caused or will cause an economic hardship on the applicant;

ii. The applicant cannot yield a reasonable return on the property if a datacenter or warehouse is not allowed;

iii. The applicant has made substantial investment in the development of a data center or warehouse that is affected by the Temporary Moratorium, which investment was made in reasonable reliance on the regulations in effect prior to the Temporary Moratorium and without knowledge of pending changes in such regulations (including this Temporary Moratorium), and based on a reasonable probability of zoning approval by the City;

iv. The datacenter or warehouse would have been allowed as a matter of right under the pre-existing Zoning Ordinance; and

v. The datacenter or warehouse as proposed complies with all other applicable City ordinances, regulations, and rules.

The Peti...