On agenda: 6/14/2022 Final action: 6/14/2022
Title: A Resolution to enter into a Agreements with the Illinois Department of Transportation, and Crawford, Murphy and Tilly for Design Phase and Construction Phase Engineering Services in the amounts of $55,300 and $114,600 for the Airfield Pavement Rehabilitation Phase 4 Project (ARR-4785).
Attachments: 1. ARR Rehab. Apron Phase 4 IDOT Letter - Cost Est. - Data Sheet, 2. Grant - pavement rehab Ph 4 05132022, 3. ARR Ph. 4 Airfield Pvmt. Rehab. Design Engr. Agrmt. for City Execution 10-1-2021, 4. ARR Ph. 4 Airfield Pvmt. Rehab. Construction Engr. Agrmt draft REVISED 2-22-22CMT executed
cover
TO: Mayor Richard C. Irvin

FROM: Steve Andras, P.E., Acting Airport Manager

DATE: May 17, 2022

SUBJECT:
A resolution authorizing the Mayor and City Clerk to execute an Agency Agreement with the State of Illinois Department of Transportation Division of Aeronautics; a not-to-exceed consultant agreement for Design Phase Engineering Services with Crawford, Murphy & Tilly in the amount of $55,300; and a not-to-exceed consultant agreement for Construction Phase Engineering Services in the amount of $114,600. All for the Airfield Pavement Rehabilitation Phase 4 Project (ARR-4785).

PURPOSE:
To obtain approval to enter into design and construction phase consultant agreements with Crawford, Murphy and Tilly as well as an agency agreement with the Illinois Department of Transportation Division of Aeronautics.

BACKGROUND:
Each fall the airport meets with the State Division of Aeronautics to prioritize its projects. This meeting is commonly referred to as the TIPs (Transportation Improvement Program) meeting.
As a result of this meeting, this project was selected by the State of Illinois to be funded as shown on the attached Program Letter.

DISCUSSION:
The total cost of this project is estimated to be $1,000,000. Our local share is five percent or $50,000. Regardless of the not-to-exceed amounts of the design and the construction consultant agreements, the maximum outlay of this project will be $50,000

Funds for this project have been set aside in our budget under CIP project D053 in account No. 504-1810-433.73-25.

IMPACT STATEMENT:
This project should have no adverse impact to the City of Aurora and should reduce the ongoing cost of maintaining the airport infrastructure.

RECOMMENDATIONS:
We respectfully request that you forward these agreements to the Committee of the Whole for its review and favorable recommendation.


cc: Finance Committee



CITY OF AURORA, ILLINOIS