cover
TO: Mayor John Laesch
FROM: Ian Wade, Capital Projects Manager
DATE: September 21, 2026
SUBJECT:
A Resolution authorizing the Director of Purchasing to enter into an agreement with RW Collins Company, 7225 W 66th Street, Chicago, IL in the amount of $121,541.50 to remove and dispose of the fueling system, which includes three underground fuel storage tanks, at 720 N. Broadway.
PURPOSE:
To obtain approval to remove and dispose of the fueling system, which includes three underground fuel storage tanks, at 720 N. Broadway.
BACKGROUND:
With the completion of the new Public Works Combined Maintenance Facility, the city's Central Garage, which will no longer be occupied and is considerably deteriorated, is anticipated to be demolished in the coming years.
As part of the demolition, the fueling area, which includes three underground fuel storage tanks, must be removed and properly disposed of.
During the excavation and removal of the tanks, the city's consultant, Fehr Graham, will be onsite to collect all environmental samples required by the Environmental Protection Agency (EPA) for site clearance.
DISCUSSION:
The city published an Invitation to Bid and two (2) responses were received by the submission deadline of September 2, 2026. Of the responses received, RW Collins Company was found to be the lowest responsible bidder in the amount of $121,541.50, which includes a $20,000 contingency to properly dispose of any contaminated soils or liquids encountered during the excavation and/or any other unforeseen conditions or additional expenses.
This work is part of CIP C123, which is approved in the 2026 budget, and will be paid using account number 236-1009-465.36-25 (Cleaning Services/Demolition), which has a current balance of $264,120.00.
The local bidder ordinance did apply to this solicitation but did not impact the award as neither of the respondents are local.
IMPACT STATEMENT:
Failure to remove the fuel system and tanks will prevent the City from...