Title: A Resolution to award the 410 Hill Av Water Main Lining project located in Wards 3 and 7 to Superior Excavating Co. in the bid amount of one hundred forty-six thousand three hundred fifty-five Dollars and zero Cents ($146,355.00).
Attachments: 1. Exhibit A - Location Map, 2. Exhibit B - Ad for Bid, 3. Exhibit C - Bid Tab_410 Hill Av, 4. Exhibit D - Superior Submittal
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: April 10, 2023

SUBJECT:
A Resolution to award the 410 Hill Av Water Main Lining project located in Wards 3 and 7 to Superior Excavating Co. in the bid amount of one hundred forty-six thousand three hundred fifty-five Dollars and zero Cents ($146,355.00).

PURPOSE:
To line the existing 6" water main that has a history of breaks.

BACKGROUND:
The location of this water main to be lined can be seen in the attached Exhibit A - Location Map. Closures of entrances to the business will be kept to a minimum during construction.

DISCUSSION:
Two bids were received, opened, and read aloud on March 29, 2023. The bid tabulations can be seen in the attached Exhibit C. The lowest responsible bid in the amount of $146,355.00 was submitted by Superior Excavating Co. The water main improvements will be funded with account 510-4058-511-73-02 (IC076) which has a 2023 budget amount of $11,950,000.00. Also included as Exhibits B & D are the advertisement for bid and Superior Excavating Co.'s submitted bid.

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

IMPACT STATEMENT:
There will be lane closures on each of these local roads during the duration of the project. Water shutdowns during the project will be planned and residences will be notified to minimize impact. Impacts to traffic and residents will be kept to a minimum.

RECOMMENDATIONS:
I request the proposed resolution awarding the contract to Superior Excavating Co. in the amount of one hundred forty-six thousand three hundred fifty-five Dollars and zero Cents ($146,355.00) be adopted."


cc: Technology & Infrastructure Committee



CITY OF AURORA, ILLINOIS

RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution to award the 410 Hill Av Water Main Lining project located in Wards 3 and 7 to Superior Excavating Co. in the bid amount of one hundred forty-six thousa...