Skip to main content

Aurora, Illinois

File #: 24-0281    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/11/2024 In control: City Council
On agenda: 5/14/2024 Final action: 5/14/2024
Title: A Resolution to award the Marion Ave., Lafayette St., and Seminary Ave. Sewer Separation project located in Wards 3 and 4 to Performance Construction & Engineering, LCC of Plano, IL in the bid amount of $1,027,780.00.
Attachments: 1. Exhibit A - Location Map, 2. Exhibit B - Bid Advertisement, 3. Exhibit C - Bid Tab, 4. Exhibit D - Contract to be executed upon City Council approval, 5. 24-055 Marion Ave., Lafayette St., and Seminary Ave. Sewer Separation Plans
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: April 22, 2024

SUBJECT:
A Resolution to award the Marion Ave., Lafayette St., and Seminary Ave. Sewer Separation project located in Wards 3 and 4 to Performance Construction & Engineering, LCC of Plano, IL in the bid amount of $1,027,780.00.

PURPOSE:
To install a new storm sewer removing stormwater from the combined sewer system at several locations including Marion Ave., Lafayette St., and Seminary Ave. Any confirmed lead water services in the project limits will be replaced as part of this project.

BACKGROUND:
A new storm sewer will be installed to remove surface drainage flows from the combined sewer system. A location map is attached as Exhibit A to show the limits of the project. This project will help satisfy the requirements associated with the City's Long Term Control Plan and the City's Illinois Environmental Protection Agency Combined Sewer System Overflow. Lead water services within the project corridor will be replaced with the approval of each homeowner.

DISCUSSION:
The proposed improvements have been publicly advertised and bid in conformance with City procedures. The advertisement for bid is attached as Exhibit B. Two conforming bids were received, publicly opened and read aloud on April 10, 2024. The bid tabulation and the contract to be executed upon City Council approval are attached as Exhibits C and D respectively.

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

Portions of the project are accounted for within two 2024 budgets. $386,200.00 within account 510-4058-511-73-02 (IC080, $3,000,000.00 Lead Water Service Line Replacement), and $641,580.00 within account 281-1856-512-73-09 (B031, $3,000,000.00 LTCP Improvements - Sewer Separation).

IMPACT STATEMENT:
Traffic will be detoured to adjacent blocks, but the increase in traffic on the adjacent neighboring blocks will be temporary and negligib...

Click here for full text