Skip to main content

Aurora, Illinois

File #: 20-0165    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/1/2020 In control: Infrastructure and Technology Committee
On agenda: 3/9/2020 Final action: 4/1/2020
Title: A Resolution authorizing the Director of Purchasing to enter into an agreement with Geneva Construction Co., P.O. Box 998, Aurora, IL 60507-0998 in the amount of $802,630.00 for the 2020 Citywide Pavement Patching for Water and Sewer Maintenance.
Attachments: 1. Exhibit A - Ad for Bid.pdf, 2. Exhibit B - W&S Patching Bid Tab.pdf, 3. Exhibit C - Geneva Const Submitted Bid.pdf
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: March 9, 2020

SUBJECT:
A resolution to award the 2020 Citywide Pavement Patching for Water and Sewer Maintenance to Geneva Construction Co., P.O. Box 998, Aurora, IL 60507-0998.

PURPOSE:
This is an annual project that is required to patch pavement in the public right of way that was damaged in relation to utility repairs such as water main breaks and sanitary sewer repairs. Geneva Construction has been awarded this contract in the past and has performed satisfactory work.

BACKGROUND:
This project was bid publicly, with an advertisement in the Aurora Beacon News on February 16, 2020. The proof of the advertisement is attached as Exhibit A. Bids were received, opened and read aloud publicly on March 1, 2020. Three bids were received with the tabulation of those bids attached hereto and incorporated as Exhibit B. The lowest responsible bid was from Geneva Construction Co. of Aurora, IL in the amount of $802,630.00. A copy of the submitted bid is attached as Exhibit C. The lowest bid came in approximately 5% below the engineer's estimate. It was anticipated that a small portion of this contract would be used to address individual utility repairs performed by contractors to take advantage of better restoration prices.

This bid is required to follow the City's Local Preference Ordinance, but since the lowest, responsible bidder is a local vendor there are no additional costs/calculations.

DISCUSSION:
This Citywide project will benefit the entire community, as it is the only contract that will be in place to repair the roadways that are damaged throughout the year due to utility repairs. This work is budgeted for on an annual basis. This contract shall have a maximum value of $802,630.00 with funds coming from the total amount remaining amount budgeted in 2020 within Account Number 510-4063-511-38-38 ($664,750.00) and $68,940 each from Account Number 510-4063-511-73-14 (S...