Title: A Resolution authorizing the Director of Purchasing to enter into an agreement with TAT Enterprises of Union, IL in the amount of $86,426.25 for the construction of an overflow parking lot at the Phillips Park Golf Course.
Attachments: 1. 26-032 Evaluation Tabulation, 2. Project Plans, 3. Exhibit 1 Bid Specifications, 4. Exhibit 2 TAT Enterprise Inc Response Document Report
cover
TO: Mayor John Laesch

FROM: Ian Wade, Capital Projects Manager

DATE: May 26, 2026

SUBJECT:
A resolution authorizing the Director of Purchasing to enter into an agreement with TAT Enterprises of Union, IL in the amount of $86,426.25 for the construction of an overflow parking lot at the Phillips Park Golf Course.

PURPOSE:
To enter into an agreement with TAT Enterprises of Union, IL in the amount of $86,426.25 for the construction of an overflow parking lot at the Phillips Park Golf Course.

BACKGROUND:
As a result of the continued success and consistently increasing patronage of the golf course at Phillips Park, the existing parking lot is no longer able to provide sufficient parking during peak season. As a result, the City is looking to construct a small overflow parking lot adjacent to the course entrance off Hill Avenue which will allow for parking of up to twenty additional vehicles.

DISCUSSION:
An invitation to bid was published and four (4) bids were submitted electronically on May 14, 2026. Of the four (4) bids received, TAT Enterprise, Inc. was determined to be the lowest responsible bidder in the total amount of $86,426.25 (see attached bid tabulation for details). This amount includes a base bid of $79,426.25 plus a $7,000 contingency to address any additional work and/or quantities deemed necessary during construction. This project was budgeted as a Decision Package in 2026 and will be paid using $60,000 from account 550-4442-451.38-05, which has a current balance of $97,168.29. The remaining funds, which will not exceed $26,426.25 and will cover the cost of the required stormwater infrastructure to be installed, will be paid using account 280-1852-512.81-90 (as part of CIP B037), which has a current balance of $5,497,947.10.

This bid was subject to Local Preference, but it did not impact the award.

Vendor has been confirmed to be in good standing with the City and does not owe any funds.

IMPACT STATEMENT:
The construction of an overf...