Attachments: 1. Exhibit A - 25-139 Location Map - S. Lincoln Ave. and Simms St. Sewer Separation, 2. Exhibit B - 25-139 Posted Bid Document - S. Lincoln Ave. and Simms St. Sewer Separation, 3. Exhibit C - 25-139 Bid Tab - S. Lincoln Ave. and Simms St. Sewer Separation, 4. Exhibit D - 25-139 Submitted Bid - S. Lincoln Ave. and Simms St. Sewer Separation
cover
TO: Mayor Richard C. Irvin

FROM: Kurt Muth, P.E., Engineering Coordinator

DATE: April 21, 2025

SUBJECT:
A Resolution to award the S. Lincoln Ave. and Simms St. Sewer Separation project located in Ward 4 to H. Linden & Sons Sewer and Water, Inc. in the bid amount of $179,748.00

PURPOSE:
To install new storm sewer removing stormwater from the combined sewer system at the intersection of S. Lincoln Ave. and Simms St.

BACKGROUND:
New storm sewer will be installed to remove surface drainage flows from the combined sewer system. A location map is attached as Exhibit A to show the limits of the project. This project will help satisfy the requirements associated with the City's Long Term Control Plan and the City's Illinois Environmental Protection Agency Combined Sewer System Overflow.

DISCUSSION:
The proposed improvements have been publicly posted and bid in conformance with City procedures. The posted bid document is attached as Exhibit B. Five conforming bids were received on April 9, 2025. The bid tabulation is attached as Exhibit C. The low bidder was H. Linden & Sons Sewer and Water, Inc. and their submitted bid is attached as Exhibit D.

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

The total amount of this project ($179,748.00) will be funded with account 281-1856-512-73-09 (B031, $3,050,000.00 LTCP Improvements - Sewer Separation).

IMPACT STATEMENT:
Traffic will be detoured to adjacent blocks, but the increase in traffic on the adjacent neighboring blocks will be temporary and negligible. At times, the adjacent local businesses may lose driveway access, but the contractor will provide adequate notice ahead of time. Water and sanitary service interruptions will not be impacted during construction of this project.

RECOMMENDATIONS:
I request the proposed resolution be adopted.