Aurora, Illinois

File #: 17-00917    Version: 1 Name: ATC Enhancements / Comcast Payment
Type: Resolution Status: Passed
File created: 10/3/2017 In control: City Council
On agenda: 10/24/2017 Final action: 10/24/2017
Title: A Resolution Authorizing the Payment to Comcast for the Undergrounding of the Overhead Utility Lines for the Aurora Transportation Center (ATC) Regional Facility Enhancement Project.
Attachments: 1. Aurora - Broadway Avenue Spring Street.pdf
cover
TO: Mayor Richard C. Irvin

FROM: Kenneth Schroth, P.E Direct of Public Works/City Engineer

DATE: October 10, 2017

SUBJECT:
Resolution Authorizing the Payment to Comcast for the Undergrounding of the Overhead Utility Lines for the Aurora Transportation Center (ATC) Regional Facility Enhancement Project.

PURPOSE:
To authorizing the Payment to Comcast for in an amount not to exceed $8,200 for the Undergrounding of the Overhead Utility Lines along the west side of Broadway Avenue for the Aurora Transportation Center (ATC) Regional Facility Enhancement Project.

BACKGROUND:
The proposal is part of the Aurora Transportation Center (ATC) Regional Facilities Enhancement Project (CIP A059). Located in downtown Aurora, the proposed improvements will help serve as a catalyst to future development. The project is comprehensive in nature and focused on renovating Broadway / IL Route 25, the ATC parking facilities, and providing a bicycle/pedestrian bridge that will span the Fox River. The vehicular improvements will include the relocation of the existing Pace Bus staging area and traffic signal to the main ATC parking facility, the reconfiguration parking stalls to add efficiency, a landscaped median in Broadway, and additional parking stalls in Lot W. The new bicycle/pedestrian bridge will provide access to the west side of the river, connect two regional trails, and provide access to additional parking for the ATC and RiverEdge Park. Please refer to the Overall Project Location attachment.

The approximately $14.7M dollar project is being funded largely by a CMAQ grant in an amount up to $11.4M, additional construction funding is being provided by the Kane County Forest Preserve in the amount of $1.65M, and the balance of the funding is to come from the 2017 GO Bond Issuance in the amount $1.65M for construction and construction engineering. Additionally, $0.7M for utility work and $1.4M for Phase I and II Engineering has been funded from the bond, and $350...

Click here for full text