Skip to main content

Aurora, Illinois

File #: 25-0762    Version: 2 Name:
Type: Resolution Status: Forwarded to Committee of the Whole
File created: 9/25/2025 In control: Finance Committee
On agenda: 10/16/2025 Final action:
Title: A Resolution awarding the Montgomery Road and Kautz Road Traffic Signal Installation project to H & H Electric Company of Franklin Park, IL for the amount of $646,164.08 and the appropriation of Motor Fuel Tax (MFT) funds for the project).
Attachments: 1. [H&H Electric Co.] Response Document Report, 2. Schedule of Prices- Bid Tabulation Comparison, 3. BLR-09110-MFT Resolution-H&H_22-00353-00-TL - PDF, 4. A-Specifications (Proposal)_22-00353-00-TL_2025.08.21, 5. B- Plans_22-00353-00-TL_2025.08.21

cover

TO:                     Mayor John Laesch

 

FROM:                     Roopa Anjanappa, Civil Engineer

 

DATE:                     October 16, 2025

 

SUBJECT:

A resolution awarding the Montgomery Road and Kautz Road Traffic Signal Installation project to H & H Electric Company and the appropriation of $646,164.08 of Motor Fuel Tax (MFT) funds for the project.

 

PURPOSE:

To award the Montgomery Road and Kautz Road Traffic Signal Installation project to H & H Electric Company and the appropriation of $646,164.08 of Motor Fuel Tax (MFT) funds for the project.

 

BACKGROUND:

The project consists of installing a new traffic signal at the intersection of Montgomery Road and Kautz Road, adding an exclusive right turn lane by widening the roadway on east leg (north side), sidewalk improvements, refresh striping & pavement markings, combination curb and gutter removal and replacement, adding appropriate signage, restoration and other miscellaneous work in accordance with the plans and specifications.

 

DISCUSSION:

The project bid was posted on September 2, 2025 through OpenGov procurement process.  The City opened bid on September 24, 2025, two bidders that bid are H&H Electric Company (bid amount - $646,164.08) and Martam Construction (bid amount $678,378.36). The lowest bid was from H&H Electric Company. 

 

Local preference does not apply to this project due to funding source. This project uses Motor Fuel Tax (MFT) Funds and would need appropriating the funds.

 

City's 2025 & 2026 budget provides funds through the following account:

GC 081                     Montgomery Rd & Kautz Rd                          203-4020-418-76-39        $646,164.08

 

IMPACT STATEMENT:

Maintenance & energy costs for proposed traffic signal is approximately $400 per month after construction is complete and when City takes signal maintenance over.

 

RECOMMENDATIONS:

Staff recommends approval of award to H & H Electric Company and appropriation of MFT funds.

 

 

cc:                     Finance Committee

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution awarding the Montgomery Road and Kautz Road Traffic Signal Installation project to H & H Electric Company of Franklin Park, IL for the amount of $646,164.08 and the appropriation of Motor Fuel Tax (MFT) funds for the project).

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, City desires to install traffic signals at the intersection of Montgomery Road and Kautz Road

 

WHEREAS, a qualified bid was received through the OpenGov procurement process and the qualified low bid was from H & H Electric Company of Franklin Park, IL, in the amount of $646,164.08.

 

WHEREAS, there is a need to appropriate Motor Fuel Tax (MFT # 22-00353-00-TL) funds for this project in the amount of $646,164.08, a copy of which resolution is attached for approval.

 

 

WHEREAS, City of Aurora fiscal year 2025 & 2026 budget provides funds through the following account:

GC 081                     Montgomery Rd & Kautz Rd                     203-4020-418-76-39      $646,164.08

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: the Director of Purchasing is hereby authorized to execute a contract with H & H Electric Company in the amount of six hundred, forty six thousand, one hundred, sixty four dollars and eight cents ($646,164.08) for the Montgomery Road and Kautz Road Traffic Signal Installation project construction and City Clerk is hereby authorized to execute Motor Fuel Tax (MFT) funds in the amount of $646,164.08, (MFT section no. 22-00353-00-TL) of which the resolution is attached.

 

BE IT FURTHER RESOLVED that the Director of Purchasing and City Clerk is hereby authorized to execute any other such documents related to advancement and completion of the said project.