Title: A Resolution Awarding EEI the Phase II Engineering Contract for the Kautz Road Multi Use Trail for an amount not to exceed $54,108.69.
Sponsors: Eric Gallt
Attachments: 1. Kautz Road Multi-Use Path_EEI Phase II Contract.pdf, 2. Kautz Bikepath Exhibit.pdf

cover

TO:                     Mayor Thomas J. Weisner

 

FROM:                     Eric J. Gallt, City Traffic Engineer

 

DATE:                     June 23, 2016

 

SUBJECT:

A Resolution Awarding EEI the Phase II Engineering Contract for the Kautz Road Multi Use Trail for an amount not to exceed $54,108.69.

 

PURPOSE:

To Approve a Resolution Awarding EEI the Phase II Engineering Contract for the Kautz Road Multi Use Trail for an amount not to exceed $54,108.69.

 

BACKGROUND:

The City of Aurora was awarded a $525,000 grant design to construct a multi-use path along the Kautz Road right of way from McCoy Drive to New York Street.   EEI had been working on the Phase I, and was asked to continue though the Phase II Engineering. 

 

DISCUSSION:

The grant received was an 80/20 split grant with the City being required to pay 20% of the construction cost.  The City opted to fund the Phase II engineering in order to make the deadlines required by the grant.

 

The Phase II engineering will be funded by way of the following accounts:

 

GB113 Kautz Road Multi-Use Path Extension                     318 4460 431 73 19                                          $ 30,000

GB113 Kautz Road Multi-Use Path Extension                     340 4460 431 73 19                      $ 10,000

GB119 Bike and Ped Enhancements                                           3404460 431 73 91                                          $ 15,000  

 

IMPACT STATEMENT:

No Impact with this Phase

 

RECOMMENDATIONS:

Staff recommends Approval of the Resolution Awarding EEI the Phase II Engineering Contract for the Kautz Road Multi Use Trail

 

 

cc:                     Alderman O’Connor, Chairman
                     Alderman Mervine
                     Alderman Bohman
                     Alderman Mesiacos, Alternate

 

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution Awarding EEI the Phase II Engineering Contract for the Kautz Road Multi Use Trail for an amount not to exceed $54,108.69.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, the City desires to complete the multi use trail connection between McCoy Drive and New York Street along the Kautz Road right of way

 

WHEREAS, the FY 2016 fiscal budget provides funding by way of the following accounts:

 

GB113 Kautz Road Multi-Use Path Extension                     318 4460 431 73 19                                          $ 30,000

GB113 Kautz Road Multi-Use Path Extension                     340 4460 431 73 19                      $ 10,000

GB119 Bike and Ped Enhancements                                           3404460 431 73 91                                          $ 15,000  

 

 

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: the Phase II Engineering Contract for the Kautz Road Multi Use Trail is hereby awarded to EEI for an amount not to exceed $54,108.69.