Aurora, Illinois

File #: 15-00402    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/6/2015 In control: City Council
On agenda: 5/26/2015 Final action: 5/26/2015
Title: A Resolution awarding the Lake Street and River Street Two Way Conversion construction to the low bidder in the amount of $2,195,147.40, Geneva Construction Co.
Sponsors: Eric Gallt
cover
TO:      Mayor Thomas J. Weisner
 
FROM:      Eric J. Gallt, City Traffic Engineer
 
DATE:      May 6, 2015
 
SUBJECT:
A Resolution awarding the Lake Street and River Street Two Way Conversion construction to the low bidder, Geneva Construction Co.  
 
PURPOSE:
To award the Lake Street and River Street Two Way Conversion construction to the low bidder, Geneva Construction Co
 
BACKGROUND:
The City has been working with IDOT for the conversion of Lake Street and River Street from one way to two way operations.   This construction project will be the conclusion of those efforts and will remove the one way traffic along this corridor.   The construction will include a jurisdictional transfer of River Street from the State of Illinois to the City of Aurora.    
 
DISCUSSION:
This work will include resurfacing of Lake Street in the affected areas, full depth pavement in the existing parking lanes, signing, striping and signal modifications.   In addition, the River Street work will include a protected bike path that will serve to close the Fox River Trail gap.
 
Two bids were received and the bid tabs are provided for your use.   The low bidder was Geneva Construction Co. at $2,195,147.40.
 
The following funds will be utilized.
 
GB086 Lake Street Conversion      340 4460 431 79 55       $  590,000
GB086 Lake Street Conversion      231 4460 431 79 55            $     20,000
GB086 Lake Street Conversion      203 4460 431 79 55            $   590,000
GB123 River Street Conversion      340 4460 431 79 62            $1,000,000
 
IMPACT STATEMENT:
The City will see a slight maintenance increase on River Street.
 
RECOMMENDATIONS:
Staff recommend approval of award of the low bid to Geneva Construction Co.
 
 
cc:      Alderman O'Connor, Chairman
      Alderman Mervine
      Alderman Bohman
      Alderman Peters, Alternate
 
 
 
CITY OF AURORA, ILLINOIS
 
RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution awarding the Lake Street and River Street Two Way Conversion construction to the low bidder in the amount of $2,195,147.40, Geneva Construction Co.
body
WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and
 
WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and
 
WHEREAS, there is a desire of the City to convert Lake Street and River Street to two way operation
 
WHEREAS, two bids were received through the open bid process and the lowest qualified bid was from Geneva Construction Company in an amount of $2,195,147.40.
 
WHEREAS,the City of Aurora FY 2015 Budget provides funding by way of the following accounts:
 
GB086 Lake Street Conversion      340 4460 431 79 55       $   590,000
GB086 Lake Street Conversion      231 4460 431 79 55            $     20,000
GB086 Lake Street Conversion      203 4460 431 79 55            $   590,000
GB123 River Street Conversion      340 4460 431 79 62            $1,000,000
 
 
 
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: awards the Lake Street and River Street Two Way Conversion construction to the low bidder in the amount of $2,195,147.40 , Geneva Construction Co.