File #: 23-0145    Version: Name: Seefried Properties / 2815 Bilter Road / Final Plat
Type: P&D Resolution Status: Final/Appealable
File created: 2/16/2023 In control: Building, Zoning, and Economic Development Committee
On agenda: 3/1/2023 Final action: 3/7/2023
Title: A Resolution Approving the Final Plat for Butterfield Phase II Unit 5A Subdivision, on vacant land located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road
Attachments: 1. Exhibit "A" Final Plat - 2023-02-16 - 2023.067, 2. Land Use Petition and Supporting Documents - 2023-02-06 - 2023.067, 3. Plat of Survey - 2023-02-06 - 2023.067, 4. Location Map - 2023-02-16 - 2023.067, 5. Appealable Sheet - Final Plat - 2023-02-23 - 2023.067

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Planning and Zoning Commission

 

DATE:                     February 23, 2023

 

SUBJECT:

A Resolution Approving the Final Plat for Butterfield Phase II Unit 5A Subdivision, on vacant land located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road (Seefried Properties - 23-0145 / NA05/1-23.067 - FSD/FPN - JM - Ward 10)   

 

PURPOSE:

The Petitioner Seefried Properties is requesting approval of a Final Plat for Butterfield Phase II Unit 5A Subdivision, located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road which includes subdividing the lot into six lots to allow for the development of a three-building data center complex.  

 

BACKGROUND:

The Subject Property is currently vacant with PDD Planned Development District zoning, which is part of the Butterfield Planned Development. 

 

The Petitioner is requesting approval of a Final Plat for Butterfield Phase II Unit 5A Subdivision, located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road.  The details of the request include a six-lot subdivision with associated easement dedications.

 

Concurrently with this proposal, the Petitioner is requesting approval of a Final Plan for Lots 1-6 of Butterfield Phase II Unit 5A Subdivision for a Warehouse, Distribution and Storage Services (3300) Use, limited to a data center complex.  The details of the request include a phased development of three electronic data center buildings consisting of two 209,967 square foot buildings and one 415,934 square foot building. An electrical substation will be constructed to support the electrical requirements of the data centers, which substation will also provide stability to the area electrical grid. In addition, a passenger vehicle electric charging area will be made available and will be located abutting Bilter Road. The lot will begin with a minimum of five spaces with plenty of spaces to grow as the need requires. An area beside the electric charging station will be available for future retail use.

 

The data center will be accessed from a full entrance on Bilter Road across from the main entrance of the church and a right-in/ right-out on Bilter Road across from the right-in/right-out access of the church. A left turn lane will be installed on Bilter Road at the full entrance. A landscaped median will be inserted along much of the roadway of Bilter Road. Additional stacking will be added to the right turn lane on Bilter Road at Eola Road. A fire access only entrance will be located on Eola Road at Prospect Drive. The developers are installing a bike path along Bilter Road along their frontage and along the detention pond to connect the Prairie Path at the Tollway Ramp to Eola Road. Seefried will also build a sidewalk on Eola Road from Bilter Road to the bridge.

 

The Landscape Plan shows that the views of the buildings and substation are heavily buffered by berms and trees. A three-to-four-foot berm will be installed on Bilter Road in front of the building and the charging station. The substation will be buffered by a ten-foot masonry wall and a five-foot berm. Adjacent to the Prairie Path will be a four-foot berm and the detention pond. Each berm and pond are landscaped with a mixture of evergreen and canopy trees. Staff worked with developers to add additional evergreen trees along Bilter Road, in front of the substation and along the Path for year-round screening. Shrub beds are at the entrances and along Bilter Road to creative attractive viewsheds.

 

Staff and developers worked to create more attractive elevations than a standard data center by adding architectural features like height variations, large expanses of spandrel glass on the front and sides, and larger glassed office space on the front. The equipment yards and substations will be enclosed by stone molded walls.

 

Staff worked with the developers to provide heavy buffering to the project through berms, masonry walls, and heavy landscaping. The traffic study provided concluded that the development would have little to no effect upon the operations of the roadways. Additional roadway improvements are being proposed to alleviate and improve traffic including a right-in/right-out access for the eastern most access, no access to Eola Road, raised landscaped median and turn lanes on Bilter. 

 

DISCUSSION:

Staff has reviewed the Final Plat Resolution petition and have sent comments back to the petitioner on those submittals.  The petitioner has made the requested revisions to these documents and they now meet the applicable codes and ordinances, with the exception of the items reflected in the conditions listed in the Staff Recommendation below 

 

POLICIES AND GUIDELINES:

The Staff’s Evaluation and Recommendation are based on the following Physical Development Policies:

 

10.0 To provide for the orderly, balanced and efficient growth and redevelopment of the City through the positive integration of land use patterns, functions, and circulation systems. To protect and enhance those assets and values that establishes the desirable quality and general livability of the City. To promote the City’s position as a regional center.

11.1 (5) To guide and promote development to areas where public utilities, public roads

and municipal services are either available or planned.

12.0 To plan and provide for the growth of the city through the integration of land use

patterns and functions that promotes complementary interactions between different land

use components.

40.1 (1) To attract and encourage industrial, office and office-research development to

planned sites where requisite public facilities are either present or proposed.

40.1 (5) To plan and promote the extension of the office and office-research corridor along the tollway in the City of Aurora.

40.1 (6) To promote attractive, well-maintained industrial and office-research areas through

landscaping and site design.  

 

RECOMMENDATIONS:

The Planning and Zoning Commission recommended CONDITIONAL APPROVAL of A Resolution Approving the Final Plat for Butterfield Phase II Unit 5A Subdivision, on vacant land located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road, with the following conditions:

 

1.) That all the comments of the Engineering Division be addressed prior to approval of

Final Engineering.

2.) That all required permits and approvals from outside agencies be obtained. 

 

ATTACHMENTS:

EXHIBITS:

Exhibit "A" Final Plat

Land Use Petition with Supporting Documents

Location Map

Legistar History Report

Legistar: 23-0145

 

 

cc:                     

Alderman Michael B. Saville, Chairperson

Alderwoman Patty Smith, Vice Chairperson

Alderman Carl Franco

Alderman Sherman Jenkins

Alderman Ron Woerman

 

 

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution Approving the Final Plat for Butterfield Phase II Unit 5A Subdivision, on vacant land located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road   

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, by petition dated February 6, 2023, Seefried Properties filed with the City of Aurora a petition requesting approval of a Final Plat for Butterfield Phase II Unit 5A Subdivision, located at 2815 Bilter Road being south of Bilter Road and west of N. Eola Road and related required documents as attached hereto as Exhibits "A"; and

 

WHEREAS, the Planning and Zoning Commission conducted a hearing on February 22, 2023, reviewed the petition and recommended CONDITIONAL APPROVAL of said petition; and

 

WHEREAS, on March 1, 2023, the Building, Zoning and Economic Development Committee of the Aurora City Council reviewed said Final Plat and the before mentioned recommendations and recommended CONDITIONAL APPROVAL of said petition; and

 

WHEREAS, the decision of the Building, Zoning and Economic Development Committee with respect to a Final Plat is subject to appeal to the City Council in the manner set forth in Chapter 43 of the Code of Ordinances, City of Aurora, Illinois, being the Subdivision Control Ordinance; and

 

WHEREAS, no person authorized under the Subdivision Control Ordinance, to appeal such decision having done so in the manner set forth in the Code, the Decision of the Building, Zoning and Economic Development Committee constitutes final action on the proposed final plat; and  

 

NOW, THEREFORE, BE IT ORDAINED by the Building, Zoning and Economic Development Committee of the City of Aurora, Illinois, finds as facts all of the preamble recitals of this Resolution and hereby grants CONDITIONAL APPROVAL of said Final Plat with the following conditions:

 

1.) That all the comments of the Engineering Division be addressed prior to approval of

Final Engineering.

2.) That all required permits and approvals from outside agencies be obtained.

 

BE IT FURTHER RESOLVED that the Building, Zoning and Economic Development Committee of the City of Aurora hereby adopts the Final Plat and related required documents as attached hereto as Exhibit "A" Final Plat along with any easement dedications deemed necessary by the Aurora City Engineer.