cover
TO: Mayor Richard C. Irvin
FROM: Kurt Muth, P.E., Engineering Coordinator
DATE: April 11, 2022
SUBJECT:
A resolution to award the 2022 Citywide Pavement Patching for Water and Sewer Maintenance to Geneva Construction Co., P.O. Box 998, Aurora, IL 60507.
PURPOSE:
This is an annual project that is required to patch pavement in the public right of way that was damaged in relation to utility repairs such as water main breaks and sanitary sewer repairs. Geneva Construction Co. has completed similar projects in the past and has performed satisfactory work.
BACKGROUND:
This project was bid publicly, with an advertisement in the Aurora Beacon News on March 13, 2022. The proof of the advertisement is attached as Exhibit A. Bids were received, opened and read aloud publicly on March 30, 2022. Three bids were received with the tabulation of those bids attached hereto and incorporated as Exhibit B. The lowest responsible bid was from Geneva Construction, Co. of Aurora, IL in the amount of $805,160.00. A copy of the submitted bid is attached as Exhibit C. The lowest bid came in approximately 1% below the engineer's estimate. It is anticipated that a small portion of this contract will be used to address individual utility repairs performed by contractors to take advantage of better restoration prices.
This bid is required to follow the City's Local Preference Ordinance, however, there were no bids received from other certified local venders.
DISCUSSION:
This Citywide project will benefit the entire community, as it is the only contract that will be in place to repair the roadways that are damaged throughout the year due to utility repairs. This work is budgeted for on an annual basis. This contract shall have a maximum value of $805,160.00 budgeted in 2022 with funds coming from the entire amount budgeted in Account Number 510-4063-511-38-38 ($694,750.00), $ 55,205.00 from Account Number 510-4063-511-73-14 (Sanitary Sewer Evaluation and Repair, IB018, 2022 Budget amount of $ 6,858,400.00), and $55,205.00 from Account Number 510-4058-511-73-02 (Water Main Evaluation, Repair and Replacement, IC076, 2022 Budget amount of $5,108,444.00).
IMPACT STATEMENT:
Construction is expected to begin in April and will continue throughout the construction season depending on the number of utility repairs that are completed. Impacts to the public will be minimal, though will consist of short-term lane closures associated with the pavement repairs and in certain cases, loss of driveway access to allow adequate time for a concrete apron or curb to cure (when applicable).
RECOMMENDATIONS:
I request the proposed resolution awarding the contract to Geneva Construction Co. in the amount of eight hundred five thousand one hundred sixty dollars and zero cents ($805,160.00) be adopted.
cc: Infrastructure & Technology Committee

CITY OF AURORA, ILLINOIS
RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution authorizing the Director of Purchasing to enter into an agreement with Geneva Construction Co., P.O. Box 998, Aurora, IL 60507 in the amount of $805,160.00 for the 2022 Citywide Pavement Patching for Water and Sewer Maintenance.
body
WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and
WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and
WHEREAS, it is necessary and desirable to repair roadways that are damaged in relation to underground utility repairs; and
WHEREAS, three qualifying bids were received, publicly opened, and read aloud on March 30th, 2022 with the tabulation of those bids attached hereto and incorporated as Exhibit B; and
WHEREAS, Geneva Construction Co., P.O. Box 998, Aurora, IL 60507 was the lowest responsible bidder with a bid in the amount of eight hundred five thousand one hundred sixty dollars and zero cents ($805,160.00); and
WHEREAS, this contract shall have a maximum value of $805,160.00 budgeted in 2022 with funds coming from the entire amount budgeted in Account Number 510-4063-511-38-38 ($694,750.00), $ 55,205.00 from Account Number 510-4063-511-73-14 (Sanitary Sewer Evaluation and Repair, IB018, 2022 Budget amount of $ 6,858,400.00), and $55,205.00 from Account Number 510-4058-511-73-02 (Water Main Evaluation, Repair and Replacement, IC076, 2022 Budget amount of $5,108,444.00).
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: The Director of Purchasing is hereby authorized to enter into an agreement with Geneva Construction Co., P.O. Box 998, Aurora, IL 60507 in the amount of eight hundred five thousand one hundred sixty dollars and zero cents ($805,160.00) for the 2022 Citywide Pavement Patching for Water and Sewer Maintenance.