Aurora, Illinois

File #: 19-0026    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/9/2019 In control: City Council
On agenda: 2/12/2019 Final action: 2/12/2019
Title: A Resolution ratifying payment to Builders Paving, LLC for a change order in conjunction with the paving of the East Ramp Parking Lot project located at the Aurora Municipal Airport in the amount of $23,357.65
Attachments: 1. East Ramp Purchase Order-Builders.pdf, 2. East Ramp Parking Lot Invoice.pdf, 3. East Ramp Parking Lot1.pdf, 4. East Ramp Parking Lot.jpg, 5. Revised East Ramp Parking Lot.pdf, 6. IMG_1978.jpg, 7. IMG_1979.jpg, 8. IMG_1984.jpg, 9. IMG_1994.jpg, 10. IMG_1995.jpg, 11. IMG_2011.jpg, 12. IMG_2028.jpg, 13. IMG_2030.jpg, 14. IMG_0040.jpg, 15. IMG_2038.jpg, 16. IMG_0039.jpg

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Steve Andras, P.E. Interim Airport Manager

 

DATE:                     January 9, 2019

 

 

SUBJECT:

A resolution ratifying payment to Builders Paving, LLC for a change order in conjunction with the paving of the East Ramp Parking Lot located at the Aurora Municipal Airport in the amount of $23,357.65.

 

PURPOSE:

To ratify payment to Builders Paving, LLC for work performed on the East Ramp Parking Lot Paving Project.

 

BACKGROUND:

This project was initially approved under resolution R18-225 and was to be constructed at the same time as the State-funded Southeast Quadrant Perimeter Roadway project by the same contractor.

There was a 5-week delay in the start of the project due to a paperwork processing issue on the part of the State Division of Aeronautics.  This pushed construction for both projects into late fall.

During the parking lot paving project it was discovered that the subgrade soils were saturated and needed to be dried and re-compacted or replaced with dry granular material.  Given the time of the year, it was evident that drying the existing subgrade was not an option.  We decided to import porous granular material and remove and haul away the bad subgrade.

The contract unit price for removing and replacing unsuitable material was $84.00 per cubic yard.  We negotiated a reduction in this price to $70.00/CY due to the large anticipated quantity.  We also reduced the size of the lot to 2,127 square yards in order to reduce the amount of required undercut as well as reduce the overall quantities to lower the cost of the project.

 

DISCUSSION:

A budget transfer from account 504-1810-433.38-01 (remaining budget amount $6,360) has been completed and the necessary funds are available in account 504-1810-433.38-05 (remaining budget amount $21,612).  The total value of work completed in 2018 for this project is $95,037.55 and will be paid for out of the 2018 budget. The remaining striping work ($1,508) will be done in 2019 and paid for out of the 2019 budget.

 

IMPACT STATEMENT:

There is no impact on the general public or other City departments and divisions.

 

RECOMMENDATIONS:

We request that this resolution be adopted in order to make the necessary payment to the contractor for work completed.

 

 

cc:                     Finance Committee

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution ratifying payment to Builders Paving, LLC for a change order in conjunction with the paving of the East Ramp Parking Lot project located at the Aurora Municipal Airport in the amount of $23,357.65..

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, the City of Aurora owns, operates and maintains the Aurora Municipal Airport; and

 

WHEREAS, the East Ramp Parking Lot Paving project was approved by the Aurora City Council under resolution R18-225; and

 

WHEREAS, unsuitable soils were encountered during construction; and

 

WHEREAS, the contractor, Builders Paving, LLC was directed to remove the unsuitable soils and replace them with dry granular material; and

 

WHEREAS, the net additional cost to the contract for the soil stabilization work was $23,357.65; and

 

WHEREAS, a budget transfer has been completed and funds are available in account 504-1810-433.38-05 for the additional cost to the contract.

 

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: the Director of Purchasing is hereby authorized to make payment to Builders Paving, LLC in the amount of $23,357.65 for a change order in conjunction with the paving of the East Ramp Parking Lot project.