Title: A Resolution authorizing the Director of Purchasing to enter into an agreement with Blinderman Construction Company, Inc., 224 N. Des Plaines Street, Suite 650, Chicago, IL, 60661 in the amount of $110,413.00 for the Vault Infill 2021 project.
Attachments: 1. Bid Tabulation 21-60, 2. Blinderman bid, 3. 21-60 RFB - Vault Infill 2021, 4. 21-60 Plans and Specifications

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Ian Wade, Capital Projects Manager

 

DATE:                     August 23, 2021

 

SUBJECT:

A resolution authorizing the Director of Purchasing to enter into an agreement with Blinderman Construction Company, Inc., 224 N. Des Plaines Street, Suite 650, Chicago, IL, 60661 in the amount of $110,413.00 for the Vault Infill 2021 project.

 

PURPOSE:

To enter into an agreement with Blinderman Construction Company, Inc. to backfill the vaults located under the sidewalk at 26 N. Broadway and 86 S. LaSalle.

 

BACKGROUND:

The City maintains an annual vault filling program which is intended to fill in individual vaults located with the public right of way underneath sidewalks in the downtown area.  The program is funded to an extent which typically allows the City to complete one vault location each year.  Each year's vault is typically selected based on safety concerns identified by the City or residents related to either aging infrastructure (typically structural steel) within the vault which provides support for the public sidewalk above or disproportionate water infiltration to the adjacent basement. 

 

The locations to be filled this year were selected based on owner request, water infiltration, and the fact that the vaults are relatively small, allowing the City to address both locations this year.

 

The City enlisted the services of a Structural Engineer to design the interior wall, and these plans were combined with City drafted specifications to create the Invitation to Bid supplied to the contractors.

 

DISCUSSION:

The invitation to bid was published and five bids were read aloud on August 16, 2021.  Of the five bids received, Blinderman Construction Company, Inc. was determined to be the lowest responsible bidder in the amount of $110,413.00.

 

The agreement for Vault Infill 2021 (Capital Project A007) will be funded using accounts 231-1830-465.38-18 (remaining account balance of $94,352.00 to be used) and 353-1830-465.73-76 ($16,061.00 of the remaining balance of $91,850.00 to be used).

 

This bid was subject to Local Preference, but the lone bid received from a local vendor was not within the allowable threshold for consideration.

 

IMPACT STATEMENT:

The sidewalk will be closed to pedestrian's traffic during construction.  Detours will be clearly marked at the nearest intersections on both sides of the project site.

 

RECOMMENDATIONS:

I request the proposed resolution be adopted.

 

 

cc:                     Infrastructure and Technology Committee

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution authorizing the Director of Purchasing to enter into an agreement with Blinderman Construction Company, Inc., 224 N. Des Plaines Street, Suite 650, Chicago, IL, 60661 in the amount of $110,413.00 for the Vault Infill 2021 project.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, Five bids for the Vault Infill 2021 project were received; and

 

WHEREAS, Blinderman Construction Company, Inc., 224 N. Des Plaines Street, Suite 650, Chicago, IL, 60661 was the low bidder in the amount of $110,413.00; and

 

WHEREAS, funding will be provided from accounts 231-1830-465.38-18 ($94,352) and 353-1830-465.73-76 ($16,061.00); and

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: authorizing the Director of Purchasing to enter into an agreement with Blinderman Construction Company, Inc., 224 N. Des Plaines Street, Suite 650, Chicago, IL, 60661 in the amount of $110,413.00 for the Vault Infill 2021 project.