Aurora, Illinois

File #: 18-0575    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/5/2018 In control: City Council
On agenda: 9/11/2018 Final action: 9/11/2018
Title: A Resolution authorizing the Director of Purchasing to execute the Contract Change Order Request Number 1 with Performance Construction & Engineering, LLC, 217 W. John Street, Plano, IL 60545 for the 77 S. Broadway Ave. Parking Structure & 65 Water St. Demolition Project.
Attachments: 1. Exhibit A - Change Order Request #1.pdf

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Kurt Muth, P.E., Engineering Coordinator

 

DATE:                     August 28, 2018

 

SUBJECT:

Resolution authorizing the Director of Purchasing to execute the Contract Change Order Request Number 1 with Performance Construction & Engineering, LLC, 217 W. John Street, Plano, IL 60545 for the 77 S. Broadway Ave. Parking Structure & 65 Water St. Demolition Project.

 

PURPOSE:

To increase the Contract by $30,000.00 from the original value of $578,000.00 to a new Contract value of $608,000.00.

 

BACKGROUND:

This change order is necessary to increase the contract value to address two unforeseen work items encountered during construction, as discussed herein. 

 

Per the bid documents, the existing brick walls on the north and south side of the parking structure were to remain in place with new brick installed in the locations where the parking deck was attached.  After removal of the parking deck, it was determined that the outer layer of brick on each wall was not structurally sound and complete removal would be required.  The remaining underlying walls were a mixture of limestone, various types of brick and sections of poured concrete with varied finishes.  Not only were the walls in poor condition aesthetically, but also structurally, as extensive repairs to the mortar joints would be required.  After analyzing various options to address the walls, the application of a spray on concrete product known as shotcrete was selected.  Shotcrete was the most cost effective option to address the deteriorated joints, and the product also addressed the aesthetic issue by providing a uniform finish to the varying materials of the existing walls.   The cost of the shotcrete was approximately $78,000 which was offset by other contract savings of approximately $81,000.  Included in that savings was the cost for the originally planned brick wall repair and approximately $10,000 of new sidewalk that will now be installed at a later date when the site is completely backfilled.    

 

The other substantial increase to the contract cost was a result of the placement of 33 additional cubic yards of structural concrete.  After the parking deck was removed, a structural engineer conducted a follow up analysis of the building and recommended that additional structural concrete be poured around the building columns.  This additional concrete would sufficiently replace the lateral support previously provided by the parking deck.  The cost for the additional concrete was $33,000, which requires a contract increase of $30,000 that is approximately 5% of the original contract amount of $578,000.

 

DISCUSSION:

This additional work will be completed using account number 353-4010-417-71-01 which has a 2018 budget amount of $3,400,000.00.

 

IMPACT STATEMENT:

Executing this change order request to increase the Contract value will allow for payment for work that was required due to unforeseen issues that arose during construction that were not previously accounted for in the contract pay items.

 

RECOMMENDATIONS:

I request this resolution be adopted.

 

 

cc:                     Alderman O’Connor, Chairman
                     Alderman Mesiacos
                     Alderman Bugg
                     Alderman Mervine, Alternate

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution authorizing the Director of Purchasing to execute the Contract Change Order Request Number 1 with Performance Construction & Engineering, LLC, 217 W. John Street, Plano, IL 60545 for the 77 S. Broadway Ave. Parking Structure & 65 Water St. Demolition Project.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, it is necessary to execute a Change Order to the Contract with Performance Construction & Engineering, LLC, 217 W. John Street, Plano, IL 60545 to increase the Contract; and

 

WHEREAS, increasing the Contract by $30,000.00 from the original value of $578,000.00 to a new value of $608,000.00 will allow for payment for completed work that was required due to unforeseen issues that arose during construction and were not previously accounted for in the contract pay items; and

 

WHEREAS, funding has been provided in account 353-4010-417-71-01 which has a 2018 budget amount of $3,400,000.00.

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: the Director of Purchasing is hereby authorized to execute Contract Change Order Request Number 1 with Performance Construction & Engineering, LLC, 217 W. John Street, Plano, IL 60545 for the 77 S. Broadway Ave. Parking Structure & 65 Water St. Demolition Project as set forth in Exhibit ‘A’.