TO: Mayor Richard C. Irvin
FROM: Christopher E. Lirot, P.E., Road & Bridge Coordinator
DATE: October 1, 2019
SUBJECT:
A Resolution to Approve Change Order #1 with Martam Construction, Inc. for the Benton and Stolp Intersection Improvements
PURPOSE:
To approve Change Order #1 to the Benton and Stolp construction contract
BACKGROUND:
The Benton and Stolp pavement is in poor condition due to various underground improvements that have taken place over the past two years, including water main replacement, sanitary sewer improvements and the installation of a new Nicor high pressure gas main. The project includes removal of a significant amount of unused pavement, new benches, lighting, plantings and overall aesthetic improvements to the surrounding area.
DISCUSSION:
Martam Construction, Inc. is currently constructing these improvements under a contract awarded by city council in the amount of $540,854.00 by Resolution R19-239 on July 23, 2019. During the course of work, it was determined that additional sidewalk, curb and pavement quantities were required to complete the work as shown on the plans. In addition, the contract did not include the Item for Work to be Ordered by the Engineer to allow for work to be added during construction for unforeseen items. The attached Exhibit A - Change Order #1 in the amount of $99,390.00 includes the revised quantities. This change order will allow work to proceed as planned and provide additional funds for engineers to make changes that may be encountered during construction.
2019 budget for account 340-1830-465-73-76, A055, started at $850,000.00. $22,928.00 will remain in the account after the change order.
IMPACT STATEMENT:
No Impacts
RECOMMENDATIONS:
Please forward this resolution to the Finance Committee for their review and recommendation for approval.
cc: Finance Committee
CITY OF AURORA, ILLINOIS
RESOLUTION NO. _________
DATE OF PASSAGE ________________
title
A Resolution to Approve Change Order #1 to Martam Construction, Inc., 1200 Gasket Drive, Elgin, IL 60120 in the amount of $99,390.00 for the Construction Contract at Benton and Stolp.
body
WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and
WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and
WHEREAS, it is necessary and desirable to complete the improvements to the Intersection of Benton and Stolp as shown in Exhibit 'B'; and
WHEREAS, the construction contract was awarded to Martam Construction, Inc., 1200 Gasket Drive, Elgin, IL 60120 on July 23, 2019 by R19-239; and
WHEREAS, Change Order #1 in the amount of Ninety Nine Thousand Three Hundred Ninety Dollars and 00 Cents ($99,390.00) is required to fully complete the work as shown and provide a contingent for additional work; and
WHEREAS, the 2019 City Budget provides $850,000.00 in account 340-1830-465-73-76 for project A055.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: that the Director of Purchasing is hereby authorized to execute a Change Order with Martam Construction, Inc. for the unit prices shown within Change Order #1 as set forth in Exhibit 'A'.