Aurora, Illinois

File #: 24-0340    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/2/2024 In control: City Council
On agenda: 5/28/2024 Final action: 5/28/2024
Title: A Resolution to award the Lebanon Street and Pearl Street Sewer Separation project located in Wards 3 and 4 to Benchmark Construction Co Inc. in the bid amount of $988,000.00.
Attachments: 1. Exhibit A - Location Map, 2. Exhibit B - Ad for Bid, 3. Exhibit C - Bid Tab, 4. Exhibit D - Advertised Bid Docs, 5. Exhibit F - Addendum No. 1, 6. Exhibit E - Contractor Submittal

cover

TO:                     Mayor Richard C. Irvin

 

 

FROM:                     Kurt Muth, P.E., Engineering Coordinator

 

DATE:                     May 13, 2024

 

SUBJECT:

A Resolution to award the Lebanon Street and Pearl Street Sewer Separation project located in Wards 3 and 4 to Benchmark Construction Co Inc. in the bid amount of $988,000.00.

 

PURPOSE:

To install a new storm sewer removing stormwater from the combined sewer system at several locations on Lebanon Street and Pearl Street.

 

BACKGROUND:

A new storm sewer will be installed to remove surface drainage flows from the combined sewer system.  A location map is attached as Exhibit A to show the limits of the project.  This project will help satisfy the requirements associated with the City's Long Term Control Plan and the City's Illinois Environmental Protection Agency Combined Sewer System Overflow. Lead water services within the project corridor will be replaced with the approval of each homeowner.

 

DISCUSSION:

The proposed improvements have been publicly advertised and bid in conformance with City procedures.  The advertisement for bid is attached as Exhibit B.  Six conforming bids were received, publicly opened and read aloud on May 1, 2024. The bid tabulation and Benchmark Construction Co. Inc’s bid are attached as Exhibits C and E.

 

This project was subject to the Local Preference Ordinance, however no local contractors submitted.

 

Portions of the project are accounted for within three 2024 budgets. $488,798 within account 510-4058-511-73-02 (IC080, $3,000,000.00 Lead Water Service Line Replacement), and $499,202 within account 281-1856-512-73-09 (B031, $3,000,000.00 LTCP Improvements - Sewer Separation).

 

 

IMPACT STATEMENT:

Traffic will be detoured to adjacent blocks, but the increase in traffic on the adjacent neighboring blocks will be temporary and negligible.  Water and sanitary service interruptions will be kept to a minimum during construction of this project.

 

 

RECOMMENDATIONS:

I request the proposed resolution be adopted.

 

 

 

cc:                     Infrastructure & Technology Committee

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution to award the Lebanon Street and Pearl Street Sewer Separation project located in Wards 3 and 4 to Benchmark Construction Co Inc. in the bid amount of $988,000.00.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, new storm sewer is desired to remove stormwater from the combined sewer system along Lebanon Street and Pearl Street; and

 

WHEREAS, the proposed improvements have been publicly advertised and bid in conformance with City procedures; and

 

WHEREAS, six conforming bids were received and read aloud on May 1, 2024, with Benchmark Construction Co Inc. submitting the lowest responsible bid in the amount of $988,000.00; and

 

WHEREAS, a portion of the project ($488,798) is budgeted for in 2024 within account 510-4058-511-73-02 (IC080, $3,000,000.00 Lead Water Service Line Replacement); and

 

WHEREAS, a portion of the project ($499,202) is budgeted for in 2024 within account 281-1856-512-73-09 (B031, $3,000,000.00 LTCP Improvements - Sewer Separation).

 

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: that the Director of Purchasing is hereby authorized to execute a contract with Benchmark Construction Co Inc. in the bid amount of $988,000.00.