Title: A Resolution Approving a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99
Sponsors: Eric Gallt
Attachments: 1. PAY APP #2.pdf

cover

TO:                     Mayor Robert J. O’Connor

 

FROM:                     Eric J.  Gallt,  City Traffic Engineer

 

DATE:                     February 8, 2017

 

SUBJECT:

Resolution approving a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99 

 

PURPOSE:

To obtain approval of a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99  

 

BACKGROUND:

In fall of 2016 the City approved a contract with Geneva Construction in the amount of $527,218.68 for the construction of a roundabout at the intersection of Highland Drive and Sullivan Road.

 

DISCUSSION:

During the course of construction, a significant amount of contaminated soils were found in the Sullivan Road right of way.   The discovery of the contaminated soil necessitated removal, special disposal, and additional backfill.   The final amount due given the additional work was $561,423.67.  The total amount of this additional work required a change order of $34,204.99.   The following funds will be utilized:

 

Cap A Roadway Improvements                      340 4460 431 73 23                                          $34,204.99                       

 

IMPACT STATEMENT:

No Impact

 

RECOMMENDATIONS:

Staff recommends approval of a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99

 

 

cc:                     Alderman O’Connor, Chairman
                     Alderman Mervine
                     Alderman Bohman
                     Alderman Mesiacos, Alternate

 

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution  Approving a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, The City of Aurora required improvements to the intersection of Highland Avenue and Sullivan Road. And

 

WHEREAS, the approved improvements required a change order

 

WHEREAS, the FY 2016 Budget proves funding by way of the following account:

 

Cap A Roadway Improvements                      340 4460 431 73 23                                          $34,204.99

 

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: approves a change order for the Highland and Sullivan Roundabout with Geneva Construction for $34,204.99.