Title: A Resolution accepting the improvements and maintenance security for New Warehouse, 2800 Diehl Rd.
Attachments: 1. 2024-01-24 Cover Letter, 2. Location Map

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Jason Bauer, P.E. - Assist. Dir. Of Public Works - Assist. City Engineer

 

DATE:                     February 13, 2024

 

SUBJECT:

A Resolution to accept the public improvements and maintenance security for the completed New Warehouse, 2021.334, 2800 Diehl Rd in Aurora, Illinois Ward 10

 

PURPOSE:

To accept the public improvements installed by the Developer of this project and to approve the establishment of the required, one year, 20% maintenance security for these improvements.

 

BACKGROUND:

This is a commercial development that constructed a warehouse in Aurora which included public improvements. In accordance with Section 43-55(a)(3) of Aurora's Municipal Code, the Developer of the Project posted a security to ensure completion of these proposed public improvements including, water main system, sidewalks and driveway approaches for the site.

 

DISCUSSION:

This development has now completed all installations, inspections and submissions that make it eligible to be recommended by the Engineering Division for final acceptance of these improvements and for the Developer to establish the required one year maintenance security. As required by Section 43-103(c) of the Municipal Code, the Engineering Division has reviewed, approved and filed as-constructed record plans of the development which depict these public improvements and has completed and approved a final site inspection of said improvements via our onsite consultant.  Based on our review and approved site inspection, it is recommended by the Engineering Division, that City Council accept the public improvements, as well as; require as a condition of this acceptance that the developer submit the required one year maintenance security at a value of 20% of the original developments security.

 

IMPACT STATEMENT:

This action adds or replaces public infrastructure - utilities to various divisions for maintenance, including the Division of Water and Sewer Maintenance; the Water Production Division; all of which have been apprised of these new or replaced utilities.

 

RECOMMENDATIONS:

Approve the acceptance of improvements and maintenance security for New Warehouse

 

 

 

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution accepting the improvements and maintenance security for New Warehouse, 2800 Diehl Rd.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, Logistics Property has completed the public improvements for said project; and

 

WHEREAS, these said improvements have been inspected during construction by the Engineering Division, or their authorized representative, and were found to be in substantial conformance with the approved plans; and

 

WHEREAS, the City Engineer has recommended acceptance of the improvements upon posting of the required Maintenance Security in the amount of $ 273,755.40

 