File #: 25-0010    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/6/2025 In control: City Council
On agenda: 1/28/2025 Final action: 1/28/2025
Title: A Resolution authorizing the Director of Purchasing to execute Change Order Number 1 to the Contract with Hoerr Construction Inc. for the 2024 Sanitary Sewer CIPP Lining project in the amount of $84,825.00.
Attachments: 1. Exhibit 1 - Change Order Request #1, 2. Exhibit 2 - Aurora 54-inch SIPL Proposal, 3. Exhibit 3 - PO 302532

cover

TO:                     Mayor Richard C. Irvin

 

FROM:                     Kurt Muth, P.E., Engineering Coordinator

 

DATE:                     January 13, 2025

 

SUBJECT:

Resolution authorizing the Director of Purchasing to execute Change Order Request Number 1 to the Contract with Hoerr Construction Inc. for the 2024 Sanitary Sewer CIPP Lining project in the amount of $84,825.00.

 

PURPOSE:

To rehabilitate an existing brick storm sewer on E. Galena Boulevard using the spray in place pipe lining method. Lining of this storm sewer would prevent future pipe failures that would likely result in much costlier dig repairs or property damage.

 

BACKGROUND:

In early November, the City had a contractor lined up to repair the brick crosswalk on E. Galena Boulevard at the Water Street mall pedestrian crossing just east of the Fox River due to settlement of the crosswalk.  During the removal process, a massive void was discovered under the brick crosswalk.  This void was caused by a 2'x2' failure in the brick storm sewer pipe approximately 12' deep. 

 

E. Galena Boulevard was immediately closed to traffic and an emergency repair was performed over the next several days.  While this repair addressed the immediate area of the failure, additional rehabilitation is desired to address the rest of the pipe and reinforce the repair made.  The City contacted the contractor that completed the 2024 cured in place pipe lining contract which was Hoerr Construction Inc.  Hoerr Construction recently provided an estimate to perform spray in place pipe lining on the brick pipe when the weather is above freezing for a few days.  The Spray in Place pipe lining method is proposed in lieu of the cured in place pipe lining method because the brick storm sewer is not circular but rectangular with an arched top.  The engineering division believes the $84,825.00 Hoerr proposal to be a fair price due to the size/shape of the pipe and the limited access to the pipe ends.

 

The engineering division is planning on bidding the 2025 CIPP sewer lining contract late January or early February.  If this extra work were to be included in that next contract, it would delay the rehabilitation of the brick pipe by a minimum of two months.

 

DISCUSSION:

This sewer to be rehabilitated is a dedicated storm sewer.  Therefore, we are requesting account 280-1852-512-81-23 (B037) be used for this rehabilitation which has an approved 2025 budget of $1,500,000.00.

 

IMPACT STATEMENT:

Failure to act quickly may lead to another section of the pipe failing which would likely result in a sinkhole along a busy section of E. Galena Boulevard downtown near the east bank of the Fox River.

 

RECOMMENDATIONS:

I request the proposed resolution be adopted.

 

 

cc:                     Technology & Infrastructure Committee

 

CITY OF AURORA, ILLINOIS

 

RESOLUTION NO. _________

DATE OF PASSAGE ________________

title

A Resolution authorizing the Director of Purchasing to execute Change Order Number 1 to the Contract with Hoerr Construction Inc. for the 2024 Sanitary Sewer CIPP Lining project in the amount of $84,825.00.

body

WHEREAS, the City of Aurora has a population of more than 25,000 persons and is, therefore, a home rule unit under subsection (a) of Section 6 of Article VII of the Illinois Constitution of 1970; and

 

WHEREAS, subject to said Section, a home rule unit may exercise any power and perform any function pertaining to its government and affairs for the protection of the public health, safety, morals, and welfare; and

 

WHEREAS, the rehabilitation of this brick storm sewer is necessary due to a recent pipe failure; and

 

WHEREAS, the changes to this contract were unforeseeable at the time of design and bidding; and

 

WHEREAS, adjusting the contract to include this additional work is necessary to expedite the rehabilitation; and 

 

WHEREAS, the City has available 2025 budget in 280-1852-512-8190 (B037) for this storm sewer improvement.

 

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Aurora, Illinois, as follows: the Director of Purchasing is authorized to execute Change Order Request Number 1 to the Contract with Hoerr Construction Inc. for the 2024 Sanitary Sewer CIPP Lining project in the amount of $84,825.00.